Ardmore WTP Rapid Restart Project

Watercare Services Ltd

Location

Auckland, New Zealand

Value

$5M +

Completed

2013

Description

Construction of new overflow capabilities to allow offspec water to be quickly discharged to waste, and then return the plant to normal operation. This required a range of work to be undertaken:

  • CLS Pipelaying
  • Removal of a section of 1962OD CLS pipe and capping
  • Drainage up to 1800NB RCRRJ pipes
  • Pipe Jacking using TBM, 1050NB
  • Large shafts up to 8m deep
  • Insitu Concrete structures up to 6m deep
  • Pneumatic actuated penstocks up to 2.5m x 2.0m
  • Electrical instrumentation and controls
  • Air system upgrade
  • Supply of three custom built 3000l air receivers

Expertise

  • Earthworks
  • Drainage
  • Open trenching
  • Large diameter CLS pipelines
  • Microtunnelled 1050NB pipes
  • Manhole construction
  • Mechanical and electrical works
  • Deep shafts,
  • Mechanical works

Return to all projects

Ready to discuss your project?

pipeline-civil-30-years

Contact

Phone us on +64 9 831 0005
Email us at admin@pipelinecivil.co.nz
Visit us at 23 Airdrie Rd, Ranui, Auckland