Ardmore TWR Enabling Works
Client
Watercare Services Ltd
Client Project Manager
Jeremy Booth
Engineer to the Contract
Sven Harlos
Engineer’s Representative
Geoff McKenzie
Design Engineer
GHD
Description
Construction of two projects to enable the major Treated Water Resilience project at Ardmore Water Treatment Plant. The scope included:
- Removal of a 1200NB flowmeter inside the plant
- Installation of electric actuators on the Hunua 2 pump station
- Installation of air valves on the Hunua 2 watermain
Expertise
- time critical shutdowns
- mechanical works
- electrical works
- building modifications
- chamber construction
- traffic control